人妻夜夜爽天天天爽欧美色院_亚洲人成网线在线播放无码_性欧美熟妇freetube中国_亚洲制服类中文字幕_欧美综合缴情五月丁香_少女的悔悟潘甜甜果冻传媒资源_国产黄色三级免费看_一级毛片在线播放免费看_日韩爱爱精品一区二区三区_青柠直播免费观看日本

您好,歡迎來(lái)到山東共贏瑞建設(shè)工程有限公司網(wǎng)站!

服務(wù)熱線

13165112299

公司動(dòng)態(tài) 當(dāng)前位置:首頁(yè)-新聞資訊-公司動(dòng)態(tài)玻璃雨棚做法介紹

玻璃雨棚做法介紹

發(fā)布時(shí)間:2024-06-19 來(lái)源:http://01888888.cn/

玻璃雨棚的整體結(jié)構(gòu)使以鋼結(jié)構(gòu)框架為主,選用的都是的鋼管。一般玻璃采用的都是鋼化玻璃,鋼化玻璃的強(qiáng)度高,承載能力強(qiáng),不容易損壞。下面帶您了解一下玻璃雨棚做法。

The overall structure of the glass canopy is mainly made of steel frame, and high-quality steel pipes are used. Generally, tempered glass is used, which has high strength, strong load-bearing capacity, and is not easily damaged. Let me take you to learn about the practice of glass canopies.

玻璃雨棚做法

Glass canopy construction method

1、加工準(zhǔn)備及下料:按照施工圖放樣,放樣和號(hào)料時(shí)要預(yù)留焊接收縮量和加工余量,根據(jù)放樣作樣板。做好鋼材矯正,鋼板預(yù)埋件及其他零件切割鉆孔及噴防腐漆處理。

1. Processing preparation and cutting: According to the construction drawing layout, welding shrinkage and processing allowance should be reserved during layout and marking, and a sample should be made according to the layout. Proper steel correction, cutting and drilling of steel plate embedded parts and other parts, and spraying anti-corrosion paint treatment.

2、測(cè)量放線:根據(jù)土建標(biāo)高基準(zhǔn)線測(cè)預(yù)埋件標(biāo)高中心線,檢查預(yù)埋件標(biāo)高偏差、左右偏差。整理結(jié)果,確定預(yù)埋件分隔的調(diào)整處理方案。沿樓板外沿彈出墨線定出預(yù)埋件頂標(biāo)高線。

2. Measurement and laying out: Measure the centerline of the embedded parts according to the civil engineering elevation reference line, and check the elevation deviation and left and right deviation of the embedded parts. Organize the results and determine the adjustment and handling plan for the separation of embedded parts. Pop an ink line along the outer edge of the floor slab to determine the top elevation line of the embedded parts.

3、預(yù)埋件安裝處理:定位預(yù)埋件安裝位置,打鉆安裝。

3. Installation and processing of embedded parts: locate the installation position of embedded parts and drill for installation.

a02e463586b78f6

4、懸掛臂安裝焊接。

4. Welding of suspension arm installation.

5、校準(zhǔn)檢驗(yàn)。

5. Calibration inspection.

6、連接受力拉索:定位拉桿基準(zhǔn)線、標(biāo)高線,按要求安裝預(yù)埋件,焊接欄桿。

6. Connecting tension cables: locate the reference line and elevation line of the tension rod, install embedded parts as required, and weld the railing.

7、不銹鋼玻璃爪安裝焊接:按設(shè)計(jì)尺寸彈出縱橫線及設(shè)計(jì)標(biāo)高,用夾具夾緊,進(jìn)行定位點(diǎn)焊,裝配完畢,焊接玻璃爪底座。

7. Installation and welding of stainless steel glass claws: Draw vertical and horizontal lines and design elevations according to the design dimensions, clamp with fixtures, perform positioning spot welding, and after assembly, weld the glass claw base.

8、防銹噴漆處理。

8. Anti rust spray painting treatment.

9、夾膠玻璃加工制作安裝,偏差不得超過(guò)規(guī)定偏差。

9. The processing, production, and installation of laminated glass shall not exceed the specified deviation.

10、調(diào)整檢驗(yàn):點(diǎn)式玻璃進(jìn)行整體調(diào)整檢驗(yàn),調(diào)整標(biāo)準(zhǔn)橫平、豎直、面平。偏差不得超過(guò)規(guī)定偏差。

10. Adjustment inspection: Point glass undergoes overall adjustment inspection, adjusting standards for horizontal, vertical, and surface flatness. The deviation shall not exceed the specified deviation.

11、然后分別進(jìn)行上下打膠、修補(bǔ)檢驗(yàn)、玻璃清洗、清理現(xiàn)場(chǎng)、竣工驗(yàn)收。

11. Then carry out upper and lower gluing, repair inspection, glass cleaning, site cleaning, and final acceptance.